File #: 19-5429    Version: 1 Name: Construction Contract-David B. Waymer, Sr. Recreation Center
Type: Consent Status: Consent
File created: 5/6/2019 In control: Asset/Facility Management
On agenda: 6/4/2019 Final action:
Title: : Construction Contract - David B. Waymer, Sr. Recreation Center
Attachments: 1. David B Waymer Gym Reno Bid Tab 04-23-2019.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

Construction Contract - David B. Waymer, Sr. Recreation Center

 

Summary

ACTION:

Award a construction contract to Hoss Contracting, Inc. in the amount of $2,190,669 for the renovation of David B. Waymer, Sr. Recreation Center

 

 

Staff Contact:                     Peter Wasmer, AIA, Project Manager

Asset and Facility Management

 

 

Presentation:                      No                                          

 

 

BACKGROUND/JUSTIFICATION:

This project is the renovation of the David B. Waymer, Sr. Recreation Center located at Holbrooks Road in Huntersville, North Carolina, between Waymer Park and the Torrence-Lytle School. The renovation includes the existing gym, lobby, restrooms, and the band/agriculture wing.The scope includes a new roof, new HVAC and electrical systems, new windows, new toilets and renovated program spaces 

 

 

PROCUREMENT BACKGROUND:

This Project was advertised on March 26, 2019 in the Charlotte Post, Charlotte Observer, and the North Carolina Interactive Purchasing System. A mandatory pre-bid meeting was held on April 10, 2019.

 

Bids were received April 23, 2019 with (3) three firms submitting bids. The lowest responsive base bidder was Hoss Contracting, Inc. at $1,978,669. The County has elected to accept alternate 1(renovation of band/agriculture wing) resulting in the total contract amount of $2,190,669 (Bid tab attached).

 

 

MWSBE Utilization:

 Subcontractors:        MBE 7.50 %    WBE 1.95%  SBE 0%

 

 

 

POLICY IMPACT:

N/A

 

FISCAL IMPACT:

Funding for this Capital Project is available from PAYGO.