Title:
Ordinance Amendment - FY2018 Library Facilities Capital Project Ordinance
Summary
ACTION:
Approve amendment to the FY2018 Authorization Library Facilities Main Capital Project Ordinance
Staff Contact: Sarah Lyberg, Financial Services Director
Presentation: No
BACKGROUND/JUSTIFICATION:
The Board adopted the FY2018 Authorization Library Facilities Main Capital Project Ordinance on June 20, 2017 for the purpose of providing funds for the New Main Library project in the amount of $65,000,000. To begin conceptual design, this capital project ordinance amendment revises the FY2018 and FY2019 funding. The County's financial commitment does not change; however, funding for FY2018 increases by $480,000, and funding for FY2019 decreases by $480,000.
PROCUREMENT BACKGROUND:
N/A
POLICY IMPACT:
N/A
FISCAL IMPACT:
N/A