Skip to main content


File #: 20-6239    Version: 1 Name: Interlocal Agreement with the Town of Huntersville
Type: Consent Status: Consent
File created: 6/17/2020 In control: LUESA
On agenda: 7/7/2020 Final action: 7/7/2020
Title: Interlocal Agreement with the Town of Huntersville
Attachments: 1. Resol_Upper Torrence_07-07-20.pdf, 2. ILA_Amended and Restated Huntersville_Upper Torrence_07-07-20.pdf, 3. Exhibit A_Upper Torrence Map_07-07-20.pdf

 

Title

Interlocal Agreement with the Town of Huntersville

 

 

Action

ACTION:

(A) Adopt Resolution authorizing execution of the amended Interlocal Agreement for the funding of Upper Torrence Tributary #1 Stream Restoration

 

(B) Receive and appropriate an additional $1,900,000 from the Town of Huntersville for its share of this joint construction project

 

 

Staff Contact:      Dave Canaan, LUESA - Storm Water Services

 

 

Presentation:      No                                             

 

 

BACKGROUND/JUSTIFICATION:

On June 5, 2017, the Board approved an interlocal agreement between the Town of Huntersville and Mecklenburg County for funding the design of the Upper Torrence Tributary stream restoration project. To date, the Town and County have designed and bid approximately 6,133 feet of stream restoration along Torrence Tributary #1 from North Mecklenburg Park to Interstate 77. The Town Project is 4,567 feet of minor system. The County Project is 1,566 feet of major system.

 

The 2015 interlocal agreement included compensation to the County from the Town of Huntersville for the Town’s portion of design cost in the amount of $390,000.  The Amended and Restated Interlocal Agreement will include compensation to the County from the Town to administer and fund the Town’s portion of construction in an amount not to exceed $1,900,000. The total amended Interlocal Agreement would be $2,290,000.  

 

 

PROCUREMENT BACKGROUND:

N/A

 

 

POLICY IMPACT:

N/A

 

 

FISCAL IMPACT:

Town of Huntersville funding of $1,900,000.00.