File #: 24-0013    Version: 1 Name: Capital Ordinance Amendment- Park and Recreation- Discovery Place
Type: Consent Status: Consent
File created: 12/21/2023 In control: Finance
On agenda: 1/17/2024 Final action:
Title: Capital Project Ordinance Amendment- Park and Recreation
Attachments: 1. 24-0013 Final Combined Signed Discovery Place Letter (EXECUTED 12-13-23).pdf, 2. 24-0013 Amend 2018 -Unit DISP.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Title

Capital Project Ordinance Amendment- Park and Recreation

 

Action

ACTION:

Amend the 2018 Park and Recreation Capital Project Ordinance to increase the budget for Discovery Place to $42,354,589.

 

 

Staff Contact:      David Boyd, CFO

 

 

Presentation:      No                                             

 

 

BACKGROUND/JUSTIFICATION:

In June 2019, Mecklenburg County and Discovery Place, Inc. executed an agreement wherein the County agreed to provide $16,000,000 to fund the design and construction of a new building and site improvements for Discovery Place.

 

Based upon the recent receipt of bids, the total cost of this project has increased to $42,354,589.

 

At the December 5, 2023 meeting, the Board of County Commissioners approved an additional contribution of $10,000,000 in County funds for the Discovery Place project. Discovery Place has agreed to contribute the remaining $16,354,589 needed to complete the project.

 

 

PROCUREMENT BACKGROUND:

N/A

 

 

POLICY IMPACT:

N/A

 

 

FISCAL IMPACT:

The County has previously allocated $16,000,000 to the Discovery Place project. The County will provide an additional $10,000,000 in funding to complete this project. Discovery Place will reimburse the County in the amount of $16,354,589 per the terms of the attached agreement.