File #: 24-0517    Version: 1 Name: Execute a contract for North Mecklenburg Recycling Center Roadway Improvements
Type: Consent Status: Consent
File created: 9/9/2024 In control: LUESA
On agenda: 10/1/2024 Final action:
Title: Execute a contract for North Mecklenburg Recycling Center Roadway Improvements
Attachments: 1. Bid Tabulation Summary, 2. 20240904_ North Meck Recycling Center Phase 2 Roadway Improvements Letter of Recommendation with Bid Tabulation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Execute a contract for North Mecklenburg Recycling Center Roadway Improvements

Action
ACTION:
Authorize the County Manager, or designee, to negotiate and execute a contract with Blythe Construction, Inc. for the North Mecklenburg Recycling Center Roadway Improvements in the amount of $2,497,974.07


Staff Contact: Jeffrey Smithberger, LUESA, Solid Waste Director


Presentation: No


BACKGROUND/JUSTIFICATION:
The North Mecklenburg Recycling Center is being expanded to the south to accommodate the future needs of waste and recycled materials management in the area as well as increase customer safety. This expansion project will enhance the entrance roadway by adding turn lanes required by the North Carolina Department of Transportation (NCDOT).


PROCUREMENT BACKGROUND:
Mecklenburg County issued a formal Invitation to Bid on July 24, 2024, for “North Mecklenburg Recycling Center Roadway Improvements”. Only one bid was received at the Suttle Ave offices of LUESA on August 16, 2024, at 2PM. That bid was returned unopened, as State law requires at least three bids for the first bid process. The project was rebid on August 22, 2024.

On September 3, 2024, one bid was received for the project from the rebid process. The bid was received from Blythe Construction Inc. This work is very specialized and requires a contractor who will perform night roadway work. Mecklenburg County staff and our consultant are satisfied that this work is fair compensation for the body of work and should move forward.

Based on the review by staff and the Consultant, Blythe Construction Inc was deemed to be the responsive bidder. Blythe Construction Inc intends to utilize Minority owned businesses for 3.4% of the bid amount and Woman owned businesses for 4.3 % of the bid amount.

Solid Waste recommends that the construction contract be awarded to Blythe Construction Inc in the amount of $2,497,974.07 (which includes $300,000 contingency) to complete the roadw...