Title
Interlocal Agreement with the City of Charlotte
Action
ACTION:
1) Adopt Resolution authorizing Interlocal Agreement for funding of Mallard Creek Stream and Sewer Project
2) Authorize the County Manager to negotiate and execute a funding agreement with the City of Charlotte
3) Appropriate $6,259,481 from the Storm Water Capital Improvement Program (CIP) Fund to the City of Charlotte for the County’s share of the Mallard Creek Stream and Sewer Project
Staff Contact: Bong Vang, LUESA - Storm Water Services
Presentation:
BACKGROUND/JUSTIFICATION:
This is a funding agreement between the City of Charlotte and Mecklenburg County for the funding of Storm Water Services’ portion of the joint project on Mallard Creek between Mallard Creek Church Road and I-485. The County will fund the construction of approximately 5,800 linear feet of stream improvements. The City will fund the construction of approximately 18,036 linear feet of sanitary sewer. The City will oversee and manage the construction of the joint project while coordinating closely with Storm Water Services as outlined in the Interlocal Agreement for funding of the Mallard Creek Stream and Sewer Project.
Charlotte Water will fund $19,694,384.00 for sewer work. Mecklenburg County Storm Water CIP funds will pay up to $6,259,481.00 for restoration of the stream. At the conclusion of the joint project, any of the County’s funding not completely utilized on Storm Water Services’ stream restoration will be promptly returned to the County.
PROCUREMENT BACKGROUND:
N/A
POLICY IMPACT:
N/A
FISCAL IMPACT:
The Stormwater CIP for DEPT: LUE FUND:8910 UNIT:3206 will fund this construction.