File #: 25-0145    Version: 1 Name: Construction Contract - Tyvola Senior Center Solar Photovoltaic Panel Installation
Type: Consent Status: Consent
File created: 2/25/2025 In control: Asset/Facility Management
On agenda: 4/1/2025 Final action:
Title: Construction Contract-Tyvola Senior Center Solar Photovoltaic Panel Installation
Attachments: 1. Tyvola PV Certified Bid Tab
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title
Construction Contract-Tyvola Senior Center Solar Photovoltaic Panel Installation

Action
ACTION:
Award a construction contract to Miles-McClellan Construction Company, Inc., in the amount of $893,535.00 for the Tyvola Senior Center Solar Photovoltaic Panel Installation



Staff Contact: Ed (Egidio) Tavares, Energy Manager, Asset and Facility Management Department


Presentation: No


BACKGROUND/JUSTIFICATION:
This project is for the installation of solar photovoltaic panels at the Tyvola Senior Center. These photovoltaic panels will generate electricity for the facility, thereby reducing the facility’s carbon footprint. This project is part of the County’s Environmental Leadership Action Plan initiative to achieve net-zero carbon by 2035.



PROCUREMENT BACKGROUND:
This Project was originally advertised on October 17, 2024, in the Charlotte Post, Charlotte Observer, Greater Diversity News, and the North Carolina electronic Vendor Portal. A mandatory pre-bid meeting was held on October 31, 2024. A bid opening was scheduled for November 21, 2024, but no bids were received.

The Project was re-advertised on November 26, 2024. A bid opening was scheduled for December 16, 2024, but again no bids were received.

The Project was re-advertised again on January 8, 2025. A bid opening was scheduled for January 30, 2025, with two (2) contractors submitting bids. The lowest responsive, responsible, bidder was Miles-McClellan Construction Company, Inc. in the amount of $893,535.00, including acceptance of Alternate No. 1 for $4,535.00.

Anticipated MWBE Utilization: 1.98%


Prime Contractor Utilization: MBE 0% WBE 0%
Sub-Contractor Utilization: MBE 0.0 % WBE 1.98%

The subcontractor MWBE contract-by-contract goals for this project are MBE: 0% and WBE 2%. Miles-McClellan Construction Company, Inc. intends to self-perform work with their own forces or subcontract with non-MWBE subcontractors for 98.02% of the work. The remaining 1.98% of the tot...